Comment on Kerse Road Bridge Closure Plans

Stirling East Councillor Chris Kane says,

clpcandidates - 6

“Network Rail initially suggested a totally unacceptable thirteen month full closure of the bridge. Through a lot of hard work from Stirling Council officers, and lobbying by Braehead Community Councillors and elected councillors, this has been reduced to a six month full closure with significant mitigation measures on affected roads.

Road safety is my number one priority and the proposed series of measures will go a long way towards this, as will the clear commitment from Network Rail and Stirling Council to spring into immediate action if something unexpected happens. 

This will have to be monitored extremely carefully.  There needs to be regular, meaningful communication with communities and affected businesses throughout the closure.   Network Rail have been told that their level of engagement with businesses in Springkerse is not up to scratch and they have committed to an immediate improvement in communication.

While this closure will cause a huge inconvenience for local residents and organisations based in Springkerse, it is important to remember that Stirling is open for business and ready to give our usual welcome to tourists and day trippers.  The further away from the closure you are, the more time you’ll have to react to the diversionary signs and less time will be added on to your journey.

Nobody thinks this is an ideal situation but at the end of the process we’re going to have a bigger, better bridge and an electrified railway with better, faster more environmentally friendly trains.”